top of page

Kettle Hall Cottage Extension

NW Groundwork were recently contracted by Nest Building Services to assist with an extension to Kettle Hall Cottage.


NW Groundwork and plant machinery ready to start work at Kettle Hall Cottage.

The team at NW Groundwork were tasked with clearing the area where the extension was to be built and then digging the footings for the new building.



The lean-to on the side of the house was removed and the driveway cleared ready to start digging the footings.


At the back of the house the hedges were taken out and the lawn area was cleared. The sloping site offered some challenges and the team had to take extra care.



The footings were dug at the side and back of the house.



The concrete was poured ready for the next phase of the build to commence.



Angelo at Nest Building Services was very appreciative of the work carried out:

"We would like to say a big thanks to Mark and his team for all their help in setting up our new project. I can honestly say it wasn't an easy foundation to dig out, but Mark and the team made it look easy while still maintaining their professionalism and health and safety at all times during the project. 


"We always look forward to working with the team at NW Groundworks as we know the job will be done right the first time. They will always go out of their way to help make the job run smoothly and easily for my team and the following trades."